Home \ Case Studies \ Quick Install for Packaging Supply and Equipment Distributor
Case Study

Quick Install for Packaging Supply and Product Distributor

  • Location Illinois
  • Building Size 15,000 Sqft

Fast Teardrop Pallet Racking Install Needed Over Holiday Weekend to Lessen Impact

A packaging supplies and equipment company with more than 100 employees needed a reliable storage solution for an unused section of their warehouse. The main challenge was scheduling - installation had to be completed over a holiday weekend to avoid disrupting daily operations in their busy facility.


Securing an installation crew on short notice, willing to work through the holiday, added another layer of difficulty. SJF handled the full coordination of products, delivery, and labor to keep the project on track.


From the first call to final planning, the process took about three weeks. Installation of the pallet racking was carried out over Memorial Day weekend and completed before employees returned on Tuesday.


The project was finished on schedule, with the new racking in place and warehouse operations running smoothly without interruption.

Results

  • Teardrop pallet rack uprights, new style teardrop beams, and wire decking
  • 1,260 pallet positions
  • Procured an install team that was available to install over a holiday weekend
  • Full project took approximately 3 weeks total to complete from first call to finished installation